Explore the wastewater treatment plant

Click on the icons below to find out more about the many features of this state-of-the-art plant. Enlarge the image to full screen by clicking the arrow icon in the top right corner.

How far we've come

Late 2023 March 2025

Progress photos

Join us on a pictorial journey of the construction.

Timeline

  • Timeline item 1 - complete

    Contracts awarded - March 2023

  • Timeline item 2 - complete

    Consent granted - September 2023

  • Timeline item 3 - complete

    Construction started - late 2023

  • Timeline item 4 - complete

    Enabling works - May 2024

    • ground works
    • site preparation
  • Timeline item 5 - complete

    Outfall Structure - April 2024

  • Timeline item 6 - complete

    UV Building - May 2024

  • Timeline item 7 - active

    Stage 2 - June 2024 - March 2026

    In this stage we will be building:

    • Main plant building
    • Bioreactor tanks
    • Pump station
    • Septage receival tanks
    • Chemical area
  • Timeline item 8 - incomplete

    Commissioning the plant - March 2026

    • Equipment testing - including pipe flushing, pressure testing, and electrical tests
    • Functional testing - components and systems are working
    • Connecting the systems - connected and checked to make sure they are working harmoniously
  • Timeline item 9 - incomplete

    Site Transferred to new consent

    No later than December 2026

  • Timeline item 10 - incomplete

    Wetlands and solar farm remediation - March - September 2026

  • Timeline item 11 - incomplete

    Site remediation - March 2026

  • Timeline item 12 - incomplete

    Unveiling event

Got a question or a comment about the wastewater treatment plant?

This is the place to ask or let us know. (max 140 characters).

You have 140 characters left
Moderation Policy


Be the first to know

Sign up for email updates.